Interpretation on clause 15 of ISO/IEC Guide 65:1996
(August 2009)
Summary
Question 1:
Is it sufficient for the CAB (Conformity Assessment Body) to require the supplier to establish a process that satisfies the requirements of clause 15 through enforceable arrangements with NO ongoing verification?
Answer: yes.
This answer was agreed by 94% of CASCO P-members voting (45 in favour out of 48 voting).
Question 2:
Does ISO/IEC Guide 65 clause 15 require the CAB to require the supplier to establish a process that satisfies the requirements of clause 15 through enforceable arrangements and then the CAB verify that the process is being maintained on an ongoing basis?
Answer: no.
This answer was agreed by 81% of CASCO P-members voting (39 in favour out of 48 voting).
Background
CASCO interpretations
- Interpretation request - ISO/IEC 17021:2006 clauses 7.5.2, 8.2.3 and 7.2.4/7.2.7 (April 2010)
- Interpretation on clauses 8.3.1, 8.3.2 d and 8.3.2 e of ISO/IEC 17011:2004 (February 2010)
- Interpretation on clause 15 of ISO/IEC Guide 65:1996 (August 2009)
- Interpretation on clause 6.2.1 of ISO/IEC 17021:2006 (July 2009)